Unitest Instruments
Compliance

Substation Testing in Singapore: SP PowerAssets and EMA Requirements

Singapore's electricity grid runs on 22 kV and 66 kV distribution networks maintained by SP PowerAssets. Substation testing in Singapore is regulated by EMA under the Electricity Act — and the instruments used by licensed electrical workers for HV equipment testing are non-negotiable. Here's what the job actually requires.

By Unitest Team·15 May 2026·6 min read

Substation Testing Singapore: The Regulatory Landscape Every Licensed Electrical Worker Must Know

Singapore's electricity distribution network is a tightly regulated, mission-critical infrastructure. SP PowerAssets — the licensed electricity transmission and distribution company, part of SP Group — operates the network of 22 kV and 66 kV substations that deliver power to every building, factory, and data centre on the island. The Energy Market Authority (EMA), operating under the Electricity Act (Cap 89A), sets the regulatory framework for how this infrastructure is maintained, tested, and operated.

Substation testing Singapore EMA requirements are not optional, and they're not bureaucratic formalities. A protection relay that hasn't been tested trips incorrectly (or worse, fails to trip) during a fault. A transformer with degraded insulation fails unexpectedly, taking out supply to an entire industrial estate or hospital. An earth grid that hasn't been tested has an unknown fault impedance — potentially lethal to anyone near the substation during a ground fault. The stakes are high, and the instruments used matter.

Key Stat

Singapore's electricity supply reliability is among the best in the world — System Average Interruption Duration Index (SAIDI) is consistently below 1 minute per customer per year. This is achieved not by luck but by rigorous preventive maintenance and testing programmes at every level of the distribution network, from 66 kV bulk supply substations to 22 kV ring main units.

Who Can Perform Substation Testing in Singapore?

Singapore's Electricity Act is clear: electrical work on high voltage installations (above 1,000 V AC) must be performed by or under the direct supervision of a Licensed Electrical Worker (LEW) with the appropriate voltage class endorsement. EMA licences LEWs in several categories: up to 1,000 V, up to 22 kV, up to 66 kV, and specialist categories for specific equipment types.

Substation owners and operators must appoint a Qualified Person (QP) — typically a professional engineer or licensed electrical engineer — who takes overall responsibility for the safe operation and maintenance of the electrical installation. All maintenance records, test results, and incident reports must be maintained by the QP and are subject to EMA inspection.

SP PowerAssets, as the network operator, has its own technical standards for the connection substations and primary substations on its network. Grid-connected substations must comply with SP PowerAssets' Grid Code requirements, which include specified maintenance and testing frequencies for protection systems, switchgear, and transformers.

Protection Relay Testing — The Heart of Substation Safety

Protection relays are the intelligence of a substation. They monitor current, voltage, and frequency on the power system and send trip signals to circuit breakers when a fault is detected. An overcurrent relay that fails to trip during a short circuit allows fault current to flow until something else operates — usually a upstream breaker, causing a wider outage — or until equipment is damaged.

Secondary Injection Testing

The most common method of protection relay testing is secondary injection — applying test currents and voltages directly to the relay inputs using a relay test set, without energising the primary power circuit. Secondary injection tests verify:

Relay test sets are specialised instruments that output precisely controlled AC currents and voltages and measure relay operating times with millisecond precision. For the test results to be meaningful, the test set must be calibrated — an output current that is 5% low means you're not actually testing the relay at the specified multiple of setting current, which could mask a relay that is slow or insensitive.

Trip Circuit Testing

Testing the relay in isolation is not sufficient. The complete protection chain — relay output, tripping relay (if present), circuit breaker trip coil, and circuit breaker mechanical mechanism — must be tested end-to-end. Trip testing verifies that when the relay issues a trip signal, the circuit breaker actually opens within the specified time. A relay that operates correctly but whose trip circuit has a high-resistance connection may send a signal that isn't strong enough to energise the trip coil reliably.

Watch Out

Numerical protection relays have internal diagnostic functions and event logs that can be invaluable during fault investigation, but they do not substitute for periodic functional testing. A relay can report healthy internal diagnostics while having a failed output contact or a defective trip circuit — issues that only physical testing will reveal.

Transformer Turns Ratio and Insulation Testing

Transformer Turns Ratio (TTR) Testing

Transformer Turns Ratio testing verifies the ratio between primary and secondary winding voltages. Deviations from nameplate ratio can indicate shorted turns in the windings — often the first sign of insulation degradation within the winding. TTR testing is performed at low voltage (typically a few hundred volts) applied to the primary, with the ratio measured by the test instrument.

Insulation Resistance Testing of HV Equipment

Insulation resistance testing of HV transformers, cables, switchgear, and motors uses a megohmmeter (insulation resistance tester) applying DC test voltage — typically 2,500 V or 5,000 V for HV equipment — and measuring the resulting leakage current to determine insulation resistance. For distribution transformers, test voltages of 2,500 V DC are standard. For 22 kV cables, 5,000 V DC or higher may be used depending on the cable construction and test standard.

The Polarisation Index (PI) test — comparing the 10-minute reading to the 1-minute reading — is particularly valuable because it characterises insulation quality beyond the simple resistance value. Clean, dry insulation shows a PI above 2.0; contaminated or moisture-affected insulation shows a PI closer to 1.0. This is important because insulation resistance alone can look acceptable on a warm day while the PI reveals underlying deterioration.

Unitest's insulation testers cover the range from 500 V to 10,000 V DC, suitable for distribution-voltage equipment testing. For HV cable and transformer testing at 2,500 V and 5,000 V DC, instruments with high-voltage interlock circuits and guard terminal facilities are essential for both safety and measurement accuracy.

What Instruments Does a Substation Maintenance Engineer Need?

A properly equipped substation testing team in Singapore typically carries:

All of these instruments must have current calibration certificates. An EMA inspection or an incident investigation will examine calibration records for the instruments used to certify that equipment is safe to operate.

Pro Tip

Always record the instrument serial number and calibration certificate number in your substation test records. If a calibration error is later discovered in an instrument you used, you need to be able to identify which test records may be affected. An instrument serial number in the record makes this forensic trail possible.

Calibration for Substation Testing Instruments

All instruments used in certified substation testing must have traceable calibration certificates. For EMA-licensed electrical work, the calibration record is part of the quality assurance chain that underlies the LEW's certification that work has been performed to the required standard.

Unitest's SAC-SINGLAS accredited calibration laboratory calibrates insulation resistance testers, multimeters, and other instruments used in HV substation testing. SINGLAS accreditation provides the traceability documentation needed for EMA compliance and SP PowerAssets maintenance records.

Contact Unitest to discuss calibration arrangements for your substation testing instrument inventory. Explore our insulation tester range and electrical testers suitable for HV substation maintenance.

Conclusion

Singapore's world-class electricity supply reliability doesn't happen by itself. It's the product of rigorous substation testing Singapore EMA requirements, professional licensed electrical workers using the right instruments, and a systematic programme of protection relay testing, transformer health monitoring, and insulation condition assessment. If you're operating or maintaining substations in Singapore, the instruments you use and their calibration status are part of the compliance record — not optional extras.

Frequently Asked Questions

What regulatory body governs substation testing in Singapore?

The Energy Market Authority (EMA) is Singapore's regulator for the electricity sector under the Electricity Act (Cap 89A). EMA licences electrical workers, sets standards for electrical installations, and regulates SP Group (which includes SP PowerAssets as the licensed electricity transmission and distribution company). Substation testing requirements are defined in the Electricity (Electrical Installations) Regulations and SP PowerAssets' grid connection and maintenance standards.

What licence is required to perform HV substation testing in Singapore?

Under Singapore's Electricity Act and the Electricity (Electrical Installations) Regulations, electrical work on HV installations (above 1,000 V) must be performed by or under the supervision of a Licensed Electrical Worker (LEW) with the appropriate HV endorsement. The LEW must hold a valid EMA licence for the relevant voltage class. Substation owners must also appoint a Qualified Person (QP) responsible for the safe operation and maintenance of the installation.

How often must protection relays be tested in Singapore substations?

EMA and SP PowerAssets maintenance standards require periodic protection relay testing, typically every 1 to 3 years depending on relay age, type, and criticality. Older electromechanical relays require more frequent testing due to mechanical wear. Numerical/digital relays have longer maintenance intervals but still require functional testing of protection functions, trip testing, and secondary injection testing to verify operating currents and times.

What insulation resistance values are acceptable for HV transformer windings?

HV transformer insulation is assessed using the Polarisation Index (PI) method — the ratio of the 10-minute insulation resistance reading to the 1-minute reading. A PI above 2.0 is generally considered good for oil-filled transformers. Absolute minimum insulation resistance values vary by voltage class and transformer size, but values below 1 GΩ at test voltage for distribution transformers warrant investigation. Temperature-corrected readings must be used for comparison against historical data.

Does Unitest calibrate instruments used for substation testing in Singapore?

Yes. Unitest's SAC-SINGLAS accredited calibration laboratory calibrates insulation resistance testers (megohmmeters), multimeters, clamp meters, and other instruments used in HV substation testing. Calibration certificates are traceable to national standards and satisfy the record-keeping requirements of EMA-licensed electrical work. Contact us to discuss calibration for your substation testing instrument inventory.

Need expert advice or a quote?

Singapore's authorised Fluke, Rotronic & Amprobe distributor — same-day response.

Request Quote →
substationEMASP PowerAssetsHVprotection relayinsulation testingSingaporeelectrical workercompliance
← Back to all articles